Wind Power Project Asking for Emergency Waiver

Wind Power Project Asking for Emergency Waiver

Photo: WNAX


The developers of a wind power project in northeast South Dakota face a seventy-five thousand dollar a day fine unless the Public Utilities Commission grants a waiver.

Crowned Ridge Wind faces the penalty if the project doesn’t start before the end of the year. Special attachments to reduce noise are required on the blades but can’t be attached because of cold temperatures.

Attorney Brian Murphy, representing the developers, said there was a communications breakdown….

Commission Chairman Gary Hanson was unhappy with the news…

The problem came up in October, but the developer didn’t notify the commission until earlier this month.

Commissioner Chris Nelson says the tight timeline is a problem…

The Commission set a special hearing for December 30th to consider the waiver on the blades.

Recent Headlines

5 days ago in Local

SOUTH DAKOTA FLU PREVENTION, STATE EPIDEMIOLOGIST OFFERS INSIGHT

SIOUX FALLS, S.D. (Dakota News Now) – With the colder weather and more time indoors, families are sharing their love…

5 days ago in Local

BILL RESTRICTS FOREIGN OWNERSHIP OF ELECTRIC FACILITIES IN SOUTH DAKOTA

PIERRE, S.D. (Michael Doorn / KELO News) – The House and Energy Committee passed two bills unanimously on Friday, one…

5 days ago in Local

STATE NEEDS TO SPEND $106 MILLION IN FEDERAL FUNDS BY END OF YEAR

PIERRE, S.D. (Makenzie Huber / South Dakota Searchlight) – South Dakota must spend $106 million in remaining pandemic relief by the…

6 days ago in Local

AS STUDENT VIOLENCE RISES, STATE WANTS DISTRICTS TO HAVE OPTIONS

PIERRE, S.D. (Bart Pfankuch / South Dakota News Watch) – Whether caused by the pervasiveness of social media, an increase…

6 days ago in Local

LAWMAKERS WORRY ABOUT FEASIBILITY, SUSTAINABILITY OF RURAL HEALTH TRANSFORMATION PLAN

PIERRE, S.D. (Makenzie Huber / South Dakota Searchlight) – South Dakota’s workforce shortage and federal limitations on a $189.5 million…