Permit Pulled for Hyde County Wind Power Project

Permit Pulled for Hyde County Wind Power Project

Photo: WNAX


Meridian Wind had an application for a one hundred seventy-five megawatt wind power project in Hyde County.

Their attorney, Brett Koencke asked the Public Utilities Commission to allow them to withdraw the application due to problems with their power connections….

Koencke says the company still plans to build the project….

Commissioner Kristie Fiegen says they are seeing more congestion in getting projects connected to power distribution networks….

The commission voted three to zero to withdraw the application but told the company they would have to submit a new application when they are ready to build.

Recent Headlines

24 hours ago in Local

SOUTH DAKOTA FLU PREVENTION, STATE EPIDEMIOLOGIST OFFERS INSIGHT

SIOUX FALLS, S.D. (Dakota News Now) – With the colder weather and more time indoors, families are sharing their love…

24 hours ago in Local

BILL RESTRICTS FOREIGN OWNERSHIP OF ELECTRIC FACILITIES IN SOUTH DAKOTA

PIERRE, S.D. (Michael Doorn / KELO News) – The House and Energy Committee passed two bills unanimously on Friday, one…

24 hours ago in Local

STATE NEEDS TO SPEND $106 MILLION IN FEDERAL FUNDS BY END OF YEAR

PIERRE, S.D. (Makenzie Huber / South Dakota Searchlight) – South Dakota must spend $106 million in remaining pandemic relief by the…

2 days ago in Local

AS STUDENT VIOLENCE RISES, STATE WANTS DISTRICTS TO HAVE OPTIONS

PIERRE, S.D. (Bart Pfankuch / South Dakota News Watch) – Whether caused by the pervasiveness of social media, an increase…

2 days ago in Local

LAWMAKERS WORRY ABOUT FEASIBILITY, SUSTAINABILITY OF RURAL HEALTH TRANSFORMATION PLAN

PIERRE, S.D. (Makenzie Huber / South Dakota Searchlight) – South Dakota’s workforce shortage and federal limitations on a $189.5 million…